Construction Updates

2015

View Gallery
January

Our framers continued hanging drywall in the hallways and patient rooms and will be finishing soon. The entry vestibule framing was completed in early December. When the drywall is completed, installation of the light fixtures will soon begin. Inside the building, the mechanical, ducting, ...

View Gallery
February

There are lots of exciting changes in the new hospital building. The visible changes include applying the color coat on the wing’s east end while installation of the window and door assemblies continues. On Saturday, January 31 st the mechanical contractor’s crane hoisted seven air ...

View Gallery
April

Over the last two months, we have seen a lot of progress in the new hospital building. The first floor fire sprinklers were completed and tested in February and now work begins on the second floor sprinkler system. Our electrical contractors installed conduit for the nurse call, fire alarm and HVAC ...

View Gallery
May

Construction work continues on our new hospital's private patient rooms and bathroom facilities. Landscaping begins on the lush garden courtyard between the existing rehabilitation hospital and the new medical/surgical wing. The enclosed corridor between the Casa Colina Diagnostic Imaging Center ...

View Gallery
July

Construction on the exterior of the building is being completed on the north and east sides while the security and protective fencing has been removed. Landscaping and beautification around the building continues. The south side of the new facility will eventually be home to a beautiful fountain, ...

View Gallery
August

Progress continues in the construction of our new acute medical/surgical hospital. The Huntair CLEANSUITE M odular Ceiling Diffuser S ystem has been installed for laminar airflow which actually removes airborne particles and contaminants away from patients during a surgical procedure. Keep watching ...

View Gallery
September

Construction on the exterior of the building was completed on the north and east sides while the security and protective fencing has now been removed. This month, landscaping and beautification around the building continues. Palm trees are being plotted in the Southwest Courtyard near the Casa ...

2014

View Gallery
December

Over the last several months, the framers continued hanging drywall in the hallways and patient rooms while inside the building the mechanical, ducting, electrical, plumbing and medical gas lines continue to be installed. The entry vestibule has also been framed. The three-coat stucco system has ...

View Gallery
November

During the last several months, our framers continued hanging drywall in the hallways and patient rooms while exterior grade drywall (Densglas) was applied to the outside of the new hospital building. The exterior windows were also installed and preparation for the stucco is in process. Inside the ...